DayPilot Pro for ASP.NET WebForms 8.3 SP1

Release date: December 5, 2016 (8.3.3553)

asp.net-gantt-chart-business-weekends.png

Improvements

  • [Scheduler] Possible to hide selected days/rows (for ViewType="Days") using BeforeResHeaderRender/e.Visible (Scheduler). (build 3546)
  • [Scheduler] [Gantt] BusinessWeekends property added (Scheduler, Gantt). (build 3548)
  • [Scheduler] Server-side image export uses Resource.Name instead of Html if the Html value wasn't customized (Scheduler). (build 3549)
  • DayPilotMonth.BeforeEventRender/e.FontColor supported. (build 3551)

Fixes

  • [Scheduler] Inplace event update forced for inline event editing - fix (Scheduler). (build 3545)
  • [Scheduler] CellWidthSpec="Auto" mode grid rendering fixed (Scheduler). (build 3547)
  • [Scheduler] Row header columns defined using RowHeaderColumnWidths and Resource.Columns exported properly / fix (Scheduler). (build 3550)

Main menu